I put in ~6KW two years ago on the old garage. 245w used Trina panels, 12 panels east facing, 12 west.
Last summer I built a new shop, and installed 30 400w Jinko units per side.
Both roofs are 5:12 pitch, and the panels face roughly east and west (not south).
I, too, ran the numbers over and over before finally putting the new shop roof with east/west faces just like the old shop.
I found covering the e&w made more power than covering a n&s, though if I could only do one face, the south won.
The old shop has ~3kw east and west, feeding into an SMA 7.7 inverter, with one MPPT input unused - the plan is to add another string on the lean-to at some point.
The new shop has two of the SMA 7.7 units.
I'm feeding 12kw into a 7.7kw inverter, but thanks to the east/west orientation, it doesn't clip output too much.
I have three strings going into each inverter - 10 East panels, with 2x10 West, and 2x10 east with 1x10 West.
I debated over and over on adding a third inverter, but decided I had to cut costs somewhere.
Ideally, I'd add a third inverter, so it would be 10east/10west, and then I'd add just a few panels on the south facing wall, vertically, maybe 5-6 panels each - that would give me more winter output, but also just "top off" the 8kw of input.
As it stands, being May right now, I have some clipping.
On 5/6 we had a sunny day.
From about 10am to 2pm my output was limited - there were spots where it dropped below peak, but my curve has the top clipped. My other array, with the two strings facing west, from 1pm to 3:30
Consider that my 6kw array peaked at only 4kw output that day - still a pretty flat top to the curve - and evenly distrubuted east/west panels - but on good days (and May is supposed to be one of my peak production periods) I'm peaking at 66% of the array, so my 12kw array should be doing 9kw but I'm capped at just under 8.
Anyhow..
I used S-5! brackets on both buildings. a Z shaped plate VB-47 stand off, then the PV mounts that clamp the frame of the panel.
On the new building, I paid attention to the Jinko specs that called for having the panel stood off the roof for fire ratings, so there's a 4x2 aluminum spacer / stand off in between.
I skipped the Iron Ridge and everything else with all of the expensive racking.
Back to the inverters - the first install was under NEC 2014 and so I have a single rapid shutdown box. The Secure Power Socket works great - I used it when the transformed was replaced when we upgraded to 400A service. The east/west arrays really flatten the curve so I can get my 2kw output most of the day (8:45 to 6pm on 5/6) - I ran an extension cord into the house and kept the computer on and working.
Note that the NEW inverters, and the NEC 2017 required module-back mounted rapid shutdown boxes DOESN'T WORK.
The inverter sends the Rapid Shutdown "turn on" signal - but when the AC is cut, it stops doing that.
The solution, which I still need to test, was to install the TIgo RSS sending unit as well - it runs on 12VDC, so when the power goes out, I'll hook a battery up to turn the rapid shutdown back on, then I should be able to use my SPS.
This time, I wired the SPS into the shop as well as outside, so we can be indoors using power..
One big advantage of the SMA string setup - I don't notice a big increase in RFI - something my other ham friends complain about. That was one specific reason I picked the SMA.
I did most of the work myself - I'm not a sparky, but I pretend to be one.
I did almost all of the 6kw install, just hiring a master electrician to add the knife-switch and a few things since I needed one to sign off for the net metering anyways.
I hired the same guy again for this job - where his guys replaced the main panel on the house, did the roof penetration for the conduit down to the inverters, and some of the wiring in there.
I hired some laborers with a man lift to help me put the 72cell panels on the 16' high roof - I did the 60-cell panels on the old garage mostly by myself, occasionally with my 11 year old helping.
I did end up adding conduit along the roof peak here and ran the PV wire inside.
I was able to use the panel pigtails to "S" may way across so that + is on the "top/north" end, and "-" is on the second-down/south end (or something like that)
So my strings are 10 panels, 5 across, two high. Then the same, but rows 3-4, and rows 5-6.
I configured it so I have "East, 3-4" with "West, 1-2, 5-6" and "East 1-2,5-6" with "West 3-4"
I was trying to minimize the impact of snow (not) melting, and by doing the east/west bit, peak production drops compared to "all east" but overall production doesn't - thus, two 7.7KW inverters being fed by 24kw of panels.
The 400w panels were running $200 each last year.
Other things to note - you'll see a 200A panel mounted to the outside of the shop.
The only thing in that panel are the two 40A solar breakers. Feed-thru lugs power the interior 200A panel, with a 200A main breaker.
The 20% rule wasn't going to work for me, so I had to make sure I protected everything so I couldn't draw more than 200A through a panel - the 200A breaker at the service entrance protects the wire to the shop. The 200A breaker inside the shop means the shop panel can only see 200A across it.
Combined, it means I won't see 280A across the exterior panel by drawing 200A from the power company and adding 80A of Solar, because the draw can only be 200A into the interior panel.
Otherwise, I was limited to a single 40A breaker (like the first install).
That was also why I had to upgrade to a 400A service - that, and I put an electric boiler in the shop for the radiant heat..
Also note, I purposefully put the panels on the old shop to the north side of the roof - anticipating I would build the shop and it would shade it.
I successfully avoided shading, even in winter.
Even here in Montana, the two 12kw setups made 200kwh each (400kwh total) in December.
January was 364 & 400.
Then ~550, ~1200, ~1500 each in Feb/March/April.
Ignoring the shop heat, I'm gross overkill on power production right now - but the shop heat will eat into that, and I was anticipating putting a strip heater in the house furnace, and contemplating adding an electric car to the fleet ( to go with the electric tractor I built)