Dont/didnt you also have to report to CCC?
we are trying to put a pedestrian bridge across a small creek and I cant believe how much bureaucratic BS and redundancy there is. Not to mention the ancestral lands BS we are now dealing with.
The Coastal Commission ? They have stopped any actual work on several critcal bridge replacements. I was always of the opinion that we should not fight it anymore and let the damn things fall into the rivers. . . . . Pay the fine for polluting the creek but shut the fucking highway off. In fact, one of those bridges is on Rte 1 Humbolt County.
edit: my only involvement was with the Drilling department in support of Engineering Services. I foundn this is one click at Gew Gull Look at this shit
https://dot.ca.gov/caltrans-near-me/...ge-replacement
So its not just the Coastal Commission but look, look at this shit
Fuck Ing Aye
Documents
The following documents can be requested by contacting Rachelle Hadley at [email protected] or 707-445-6417.
FINAL Environmental Document
Draft Environmental Document
- Final Environmental Impact Report/ Environmental Assessment- March 2020
Technical Studies
- Draft Environmental Impact Report/ Environmental Assessment- October 2019
Layouts
- Air Quality Analysis - May 2014
- Air Quality Memo - Updated March 2019
- Analysis of Potential Airborne Construction Noise - September 2014
- Arborist Report - October 2014
- Arborist Report - Updated July 2019
- Asbestos-containing Material and Lead-containing Paint Survey - September 2010
- Debris Analysis - March 2016
- Environmental Document Assessment Memo - Noise - April 2014
- Hydraulic Report - September 2016
- Hydraulic Report - March 2017
- Hydroacoustic Assessment - June 2017
- Initial Site Assessment - December 2001
- Initial Site Assessment - September 2004
- Initial Site Assessment - March 2008
- Initial Site Assessment - March 2015
- Initial Site Assessment - January 2019
- Literature Review - Calculated vs. Measured Bridge Scour - January 2017
- Natural Environment Study - June 2017
- Natural Environment Study - Updated September 2019
- Noise Memo - February 2019
- Paleontological Identification/Evaluation Report - January 2017
- Paleontological Identification/Evaluation Report - Updated September 2019
- Paleontological Identification/Evaluation Report - Addendum May 2017
- Public Access Feasibility Report - July 2019
- Preliminary Foundation Report - January 2014
- Preliminary Geotechnical Report - July 2005
- Preliminary Site Investigation Report - September 2009
- Preliminary Site Investigation Report - November 2010
- Scour Analysis - Updated June 2019
- Scour Effects Analysis Report - June 2017
- Sediment Distribution - July 2016
- Structures Preliminary Geotechnical and Preliminary Seismic Report - December 2008
- Transportation Management Plan - March 2015
- Transportation Management Plan - Updated September 2018
- Visual Impact Assessment - July 2015
- Visual Impact Assessment - Updated July 2019
- Water Quality Assessment - Revised May 2017
- Water Quality Assessment - Updated February 2019
- Western Pearlshell Mussel Impact Assessment - June 2017
- Western Pearlshell Mussel Impact Assessment - Updated June 2019
- Alternative 1- Cast-in-Place on downstream alignment
- Alternative 2- Pre-Cast on downstream alignment
- Alternative 3- Cast in place on the existing alignment (Jack and Slide construction option (3A) and Panel Bridge Construction Option (3B))
- Habitat Communities
- Wetland Communities
More edit: there is more. Bureaucracy Porn !!!
Last edited: