Time for another update. Ill work on trying to be more consistent in it.
Last update had the formwork up and ready for the concrete. Couples photos of the pour.
Stripped the formwork and that's how we left it for the winter.
We raced in the 2024 King of the Hammers and had an absolute blast. Check out our instagram for some more updates on that.
Anyways, that was a big money and time suck, but we got back to business on the shop early.
We pre framed and sheeted the walls on the ground to be ready for one big weekend. With the help of some amazing friends and family, we were able to stand the walls, raise the trusses, and sheet the roof over a weekend.
After we got the walls up, we moved into electrical after getting the overhead doors, and metal ordered. We decided to drop down to 2 overhead doors. one 14x14, and one 12Hx10W in front of the lift. Steel man door rather than a standard house door.
Electrical: I'm definitely going overkill on the plugs, as I have always hated looking for somewhere to plug in. North wall (Right wall of photo above) will get the work bench and will have 5 outlets, with 2 as doubles. These are wired on an individual 20A circuit. West wall is getting 3 30A plugs for mills, lathes, ironworkers, along with a dedicated 20A line for 6 outlets along ground level, and 2 more for the mezzanine when I put that in. Also wired a 30A plug in for a compressor on the mezzanine. South and East wall outlets are 1 circuit with 8 outlets, with 1 on each side of the overhead doors. Wiring the 50A plug for the welder between the overhead doors so that I can use it anywhere including outside. Adding 2 exterior outlets on the overhead door side, along with 2 exterior lights, 1 over the man door, and 1 between the overhead doors.
Interior lighting is going to be 12 150W UFO LED lights. Works out to almost 300,000 lumens. Hope to be able to handle a surgery or 2 if needed lol. They are dimmable so will also install a dimmer to be able to adjust if necessary.
Let me know if you have any electrical suggestions. Going for Rough-In inspection this week.
Last weekend we worked on the metal, and was able to get the roof and wall metal up. Makes me very excited to see this thing start to get finished. Wedding is T-3 Months.
Since there is always some variance in the metal, we decided to wait to order some of the trim (outside corners and gable end) until we know exactly how the metal ribs worked out. Trim should be in this week and they are delivering all the interior insulation (R20) and the OSB for the ceiling and walls.
Sheeted over the man door, since we didn't have it onsite yet, and not exactly sure what the finished sizing of it is.
Overhead Doors are also coming in this week. Trying to decide if we should install them before the slab is done or wait until after. Based on life scheduling, we are thinking the slab will be going in late May. Plan is to basically have the entire interior done before we put the slab in. We are stuck waiting on clay to dry, so may as well get the insulation, poly and osb on and painted.
Heat will be radiant floor heating. Anyone have suggestions on Boilers?